Hyperscale data center moratorium

De Pere, WI

Summary

The proposed 12-month moratorium wasn't ready in time — it will land on the September Plan Commission agenda.

At a glance

Total mentions
9
Last 30 days
1

Discussed at 1 meeting in the last 60 days; most recently Sep 28, 2026.

Impact analysis

💰Financial impact

No direct cost, though the moratorium period will fund staff research time into regional data center impacts.

✅Who benefits

Residents and officials who want time to write rules before data centers can be proposed in De Pere.

⚠️Who could be affected

Data center developers could face a temporary moratorium and rezoning hurdles tied to the comprehensive plan.

Mentions & discussions (9)

MeetingNov 4, 2026

Common Council - Nov 4, 2026

The Council will consider a resolution related to enacting a development moratorium — a temporary halt on some development activity. Details of scope and duration are not in the published materials.

Spectrum NewsSep 29, 2026

De Pere, Milwaukee advance 1-year data center moratoriums

De Pere, Milwaukee advance 1-year data center moratoriums Spectrum News

MeetingSep 28, 2026approved

Plan Commission - Sep 28, 2026

De Pere is pumping the brakes on data centers before any show up. The city's only plausible site lacks water capacity, and the comp plan update would steer that land toward housing and mixed-use instead. The council still needs to hold a public hearing and adopt an ordinance, possibly in November.

MeetingAug 24, 2026

Plan Commission - Aug 24, 2026

The proposed 12-month moratorium wasn't ready in time — it will land on the September Plan Commission agenda.

MeetingJul 27, 2026

Plan Commission - Jul 27, 2026

Staff is still drafting a possible 12-month pause on hyperscale data centers to buy time for zoning rules — expect it back in August.

MeetingJun 22, 2026

Plan Commission - Jun 22, 2026

The city wants a 12-month timeout on hyperscale data centers while it finishes its comprehensive plan and researches how — or whether — such facilities should fit in De Pere. Staff stressed none is currently pursuing the city and existing zoning offers little room for one, but the moratorium would add guardrails. A draft ordinance comes in July, with a public hearing and council vote after that.

MeetingJun 9, 2026

Sustainability Commission - Jun 9, 2026

De Pere is figuring out how it would handle a data center proposal — no NDAs, no current zoning category, and hyperscale facilities that don't fit the comprehensive plan. A narrowly focused moratorium may go to the Plan Commission June 22 so the comprehensive plan update can finish first. It would ultimately need Common Council approval with a 30-day public hearing.

MeetingApr 14, 2026

Sustainability Commission - Apr 14, 2026

Commissioner Leonard is drafting a data center proposal for the Common Council; it will come to this commission first. This follows her earlier research on non-disclosure agreement ordinances in other states.

MeetingJan 13, 2026

Sustainability Commission - Jan 13, 2026

After a developer withdrew the proposed Greenleaf Center data center, Commissioner Leonard warns similar projects could still target the area. She'll research whether De Pere and neighboring communities are vulnerable and bring the topic back to the commission.

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for De Pere, WI

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.